How Construction Costs, Labor & Supply Chain Pressure Hit Development Budgets

Cost increases raise the dollars needed to deliver a fixed scope, and labor or material shortages stretch the calendar. A longer calendar adds carry and overhead on top of the price change. The budget effect is the price move on the exposed packages plus the duration move on everything charged by the month, and a contingency sized for the first can be consumed by the second.

Why subcontract terms can signal cost pressure before prices do

Cost pressure on a development often reaches the contract before it reaches a published price. Some contractors expect subcontractors to ask for protective language if oil stays near $100 per barrel for six or more months.

The earliest warning sits in the terms of deals being negotiated three to six months out, if the conflict behind the oil spike persists. A budget built from bids gathered before that window reflects the terms of the earlier market, so the bid date matters as much as the bid amount.

Escalating materials and construction costs, together with supply chain delays, rank among the biggest challenges in financing development. The pairing is logical, because one problem lands on the cost line and the other lands on the calendar.

Why the denominator decides how large a material shock looks

A materials increase is measured against a base, and the choice of base changes the headline. One ground-up garden scenario in the Southeast estimated that higher material prices, including lumber and drywall, would add 2.4% to the total project budget.

Land and financing costs sit in the total but do not move with commodity prices. They dilute the ratio, so the same dollar increase reads as a larger percentage of hard costs than of the total budget.

Shortages and price swings in items such as lumber and electrical equipment have caused project delays and higher development costs. A package therefore carries two exposures: the price paid and the date the item arrives.

Labor cost is hours multiplied by rate, and both move

Total labor cost equals paid hours multiplied by the hourly cost. A wage increase changes the second term. A shortage of crews can raise the rate through premium pay and overtime and can add hours through lost efficiency, and a thin crew also needs more calendar time to deliver the same hours.

In one survey series, six in ten construction firms reported raising base pay for craft workers. Construction job openings rose from 348,000 to 459,000 over one year, and the opening rate moved from 4.3% to 5.4%.

Another measure put the labor needed to meet demand in one year at approximately 546,000 workers, after monthly openings averaged more than 390,000 in an earlier year. In a separate survey, four of five firms expected qualified workers to stay difficult to find or become harder to find.

The cost reaches the owner through two channels: a higher rate in the subcontract price and a longer duration in the schedule.

“A shortage of construction and logistics workers has increased the cost of construction for developers and hampered the expansion and profitability of warehouse and distribution centers.”

NAIOP publication

How a late delivery turns into a monthly cost

A late delivery extends completion only when it pushes dependent work past the time available. Delivery slippage and completion slippage are different measures.

The sequence runs in steps. An item has a needed-by date for installation. If delivery moves past that date, installation moves, and every activity that waits on that installation faces its own timing test. The delay that survives to the end of the chain is the completion delay.

Float is the time an activity can move without changing the completion milestone. A slip inside float uses up flexibility and leaves the finish date alone, but the consumed float is gone when the next delay arrives.

Budget exposure follows the cost terms attached to the extra months. Charges that accrue each month grow with every added month, while a fixed fee stays fixed. Inability to access materials and labor can therefore damage both the construction budget and the timeline.

Shipment and arrival are also different events. Shipment marks departure from the supplier and arrival marks receipt at the destination, and neither means the item is ready to install.

“If we are unable to access materials and labor to complete our construction projects within our expected budgets and meet our or our development partners’ and tenants’ demands and expectations in a timely and efficient manner, our results of operations may be adversely impacted.”

Ventas Annual Report, Ventas

How exposure differs by property type and code environment

Material intensity differs by product. An average single-family home uses 439 pounds of copper and a multifamily unit uses 278 pounds, a 37% difference per unit. The gap is 161 pounds, so a copper price move reaches a single-family budget with more force per unit than a multifamily budget.

Warehouse and distribution development adds an operating question. A shortage of logistics workers has constrained expansion and profitability, so a finished building can still miss its operating plan. Plants built for lease face a similar issue where manufacturing workers are scarce, particularly in rural areas.

Regulation is its own cost line. In one multifamily survey series, building code changes over the past 10 years averaged 11.1% of total development costs, the highest average among the regulatory items measured. An average across many projects does not give the figure for a single site.

Deal stage changes the question as well. Before contracting, a price stress tests the estimate; after contracting and ordering, the tests move to scope, adjustment terms and delivery performance. Permitting red tape can also push project starts out by several years, which moves the whole budget into a later cost environment.

Worked example: a hypothetical $50 million development under price and schedule stress

The hypothetical budget totals $50 million, with 60% funded by debt. Debt equals $50 million multiplied by 60 divided by 100, or $30 million. Equity is $50 million minus $30 million, or $20 million. Debt stays fixed at its commitment, so any gap lands on equity.

The budget holds land and closing at $9 million, soft costs at $6 million, hard costs at $30 million, carry and a contingency of $500,000. Carry covers interest and site overhead, held flat at $250,000 per month for 18 months. Base carry is $250,000 multiplied by 18, or $4.5 million. The check is $9 million plus $6 million plus $30 million plus $4.5 million plus $500,000, which equals $50 million.

Hard costs split into $12 million of materials, $11 million of labor and the remainder. The remainder is $30 million minus $12 million minus $11 million, or $7 million.

Case A is a price shock only, with no change to the schedule. Materials rise 10%, so the increase is $12 million multiplied by 10 divided by 100, or $1.2 million. Labor rises 8%, so the increase is $11 million multiplied by 8 divided by 100, or $880,000. Combined, the hard-cost increase is $1.2 million plus $880,000, or $2.08 million.

The contingency absorbs $500,000, leaving a gap of $2.08 million minus $500,000, or $1.58 million. The increase equals $2.08 million divided by $50 million multiplied by 100, or 4.16% of the total budget, and $2.08 million divided by $30 million multiplied by 100, or 6.93% of hard costs.

Case B keeps the same price shock and adds a three month slip from late deliveries and thin crews. Construction then runs 18 plus 3, or 21 months. Extra carry is $250,000 multiplied by 3, or $750,000. Total stress is $2.08 million plus $750,000, or $2.83 million, which is $2.83 million divided by $50 million multiplied by 100, or 5.66% of the total budget.

After the same $500,000 contingency, the gap is $2.83 million minus $500,000, or $2.33 million. A price-only test understates it by $2.33 million minus $1.58 million, or $750,000, which is exactly the extra carry.

Measured against the $20 million of equity, Case A is $1.58 million divided by $20 million multiplied by 100, or 7.9%. Case B is $2.33 million divided by $20 million multiplied by 100, or 11.65%. The delay raises the equity call from 7.9% to 11.65% with no change in the price shock.

Budget mistakes that hide the remaining funding gap

Applying a scenario percentage to the wrong base misstates the exposure. The 2.4% materials scenario is stated against a total project budget. In the worked case the same dollars are 4.16% of the total and 6.93% of hard costs, so a project with a different hard-cost share needs its own arithmetic.

Stressing price and leaving duration alone produces a gap that is too small. Material shortages cause delays as well as higher costs, and in the example the omitted carry is $750,000 on a $2.33 million gap.

Reading a wage headline as the labor cost leaves out the hours term. Cost equals hours multiplied by rate, and a thin crew lengthens the hours on the calendar even when the hourly rate holds. With the opening rate moving from 4.3% to 5.4% in one year, both terms are in play.

Carrying a material mix from one product type to another distorts the stress. Replacing a multifamily unit’s 278 pounds with a single-family figure of 439 pounds inflates the copper line by 161 pounds per unit, so a project budgeted that way carries a materials reserve that does not exist and can mask the true funding gap elsewhere in the capital stack.

Using bids gathered before a cost shock as current pricing ignores that subcontract terms can change months before prices do. A bid is a snapshot of one date and one set of terms.

Treating an average as a project input is a further error. The 11.1% average code-change cost is a sample measure across multifamily projects, and one site can sit well above or below it.

Checklist questions for a construction budget review

Which packages are still estimates, and which are priced? The answer shows where price uncertainty remains open.

What base is each percentage measured against? A shock stated against total budget and the same shock stated against hard costs differ by the share of fixed items.

Which delivery dates feed dependent work? A late item matters in proportion to the activities waiting on it.

How much float remains on those activities? Float already consumed by earlier slips is unavailable for the next one.

Which costs accrue by the month? Their size determines how much each added month adds to the funding need.

How were the crew hours estimated, beyond the rate? Total labor cost needs both terms, and a thin crew lengthens the calendar.

When were the subcontract bids gathered, and what terms did they carry? Protective language can appear in later negotiations before it shows in prices.

Does the stress test hold capital and fees constant across cases? A common basis makes the incremental effect of price and delay visible.

Where does a gap land once the contingency is spent? With debt fixed, the answer points to equity or a scope change.

Sources
  • Why the Oil Spike May Not Shock Your Next Buyout, Origin Investments (link)
  • Bank of America’s Maria Barry On Financing Affordable Housing Post-COVID, Commercial Observer (link)
  • Navigating Tariff Pressures and Multifamily Investment Opportunities, Origin Investments (link)
  • Welltower publication (link)
  • NAIOP publication (link)
  • Economic impacts of cre, NAIOP (link)
  • How Rising Construction Costs are Impacting Real Estate Development, Naiop (link)
  • Ventas Annual Report, Ventas (link)
  • NMHC publication (link)
  • Q&A with Berkadia’s Dori Nolan on Multifamily’s Tremendous, Connect CRE (link)

Talk to Richard